Q5) Consider 3 Processes P1, P2 And P3, And 3 Types Of Resources R1, R3 And R2. The Resources Are Having 1 Instance Each. P1 Is Holding R1 And R3, P2 Is Holding R2 And Requesting For R1 And R3, P3 Is Requesting For R1 As Well As R2. A) Draw A Resource All
Q5) Consider 3 processes P1, P2 and P3, and 3 types ofresources R1, R3 and R2. The resources are having 1 instance each.P1 is holding R1 and R3, P2 is holding R2 and requesting for R1 andR3, P3 is requesting for R1 as well as R2.