3:007 e-learning.gju.edu.jo There are 4 jobs in a 4 person office that must be done as quickly as possible. The supervisor has used the assignment method to assign people to jobs. The original matrix which shows the expected completion time (in minutes) for each person for each job, is shown below. Which person should be assigned to which job? should be assigned to Ruth Job Job should be assigned to Steve should be assigned to Valerie Job Job should be assigned to Wayne How long will all jobs take in total? minutes Job Wayne Valerie Steve Ruth A 16 52 34 22 B 26 56 8 52 с 76 38 36 30 D 38 52 48 20 Next