3 А 5 4 с D B Based On The Activity Network Pictured, What Is The BEST Statement? O A. Activity B Is A Critical Activity And Will Start At Day 1 Or 2 O B. Activity C Will Start At Day 4 And Has 1 Day Slack Time O C. Activity D Is A Critical Activity And W


3 А 5 4 с D B Based on the activity network pictured, what is the BEST statement? O a. Activity B is a critical activity and will start at day 1 or 2 O b. Activity C will start at day 4 and has 1 day slack time O c. Activity D is a critical activity and will start at day 9 O d. Activity A can start at day 1 or day 2