A project has following estimated data: Price - S60 per unit; variable cost - $30 per unit: Fixed cost-$100,000, Company has borrowings of $100,000 at a rate of 10% Calculate the combined leverage of the project when units sold are 10,000 units. a 1.58 b.

匿名用户 最后更新于 2021-11-29 14:53 金融Finance

A project has following estimated data: Price - S60 per unit; variable cost - $30 per unit: Fixed cost-$100,000, Company has borrowings of $100,000 at a rate of 10% Calculate the combined leverage of the project when units sold are 10,000 units. a 1.58 b. 0.63 c. 1.50 d. 1.05