Use Table 1 to answer this question. XYZ Corporation hasprovided the following data from its activity-based costing system(Table 1). The company makes 400 units of product ABA a year,requiring a total of 690 machine-hours, 35 orders, and 10inspection-hour

匿名用户 最后更新于 2021-11-19 19:23 会计Accounting

Use Table 1 to answer this question. XYZ Corporation hasprovided the following data from its activity-based costing system(Table 1). The company makes 400 units of product ABA a year,requiring a total of 690 machine-hours, 35 orders, and 10inspection-hours per year. The product's direct materials cost is$35.72 per unit and its direct labor cost is $29.46 per unit.According to the activity-based costing system, the average cost ofproduct ABA is closest to:

Select one:

a.$92.49 per unit.

b.$94.11 per unit.

c.$95.69 per unit.

d.none of the given answer.

e.$65.18 per unit.

.

.

Use Table 2 to answer this question. XYZ Corporation hasprovided the following data from its activity-based costing system(Table 2). The company makes 430 units of product ABA a year,requiring a total of 1,120 machine-hours, 35 orders, and 40inspection-hours per year. The product's direct materials cost is$49.81 per unit and its direct labor cost is $12.34 per unit. Theproduct sells for $140 per unit. According to the activity-basedcosting system, the product margin for product ABA is:

Select one:

a.$5,752.10.

b.$4,290.10.

c.$3,602.10.

d.$7,902.10.

e.none of the given answer.

.

.

Use Table 3 to answer this question. XYZ Co uses anactivity-based costing system with three activity cost pools. Thecompany has provided the following data concerning its costs andits activity based costing system (Table 3). How much cost, intotal, would be allocated in the first-stage allocation to theCutting activity cost pool?

Select one:

a.$215,400

b.$192,100

c.$326,300

d.$254,600

e.none of the given answer.

please use table to answer Q1,2,3

Table 1 Activity Cost Pool Assembly Processing orders Inspection Total Cost $ 942,480 $ 85,050 $ 126,854 Total Activity 66,000 machine-hours 1,800 orders 1,820 inspection-hours Table 2 Activity Cost Pool Assembly Processing orders Inspection Total Cost $ 1,114,920 $ 47,016 $ 107,328 Total Activity 57.000 machine-hours 1,800 orders 1,560 inspection-hours Table 3 Costs: Factory Rent Factory Depreciation Factory Utilities Total $ 373,000 150,000 250,000 $ 773,000 Distribution of resource consumption: Total Activity Cost Pools Fixing Cutting Polishing 60% 20% 20% 35% 20% 45% 20% 60% 20% Factory Rent Factory Depreciation Factory Utilities 100% 100% 100% Scroonchot

已邀请: